| UFR
/ CSD joint project for the university hospital unit (CHU) in Clermont-Ferrand (63) €15.2 MILLION- 9,900 m² Project owner: RECTORAT DE L'ACADEMIE & CHU DE CLERMONT Architect: Philippe GAZEAU Nature of the operation: Joint construction of the Odontology Training and Research Unit and Dental Care Centre on the site of the Clermont-Ferrand CHU Mission: Project management for structure engineering, roads, CVC, Fluids, High and low currents, Elevator devices, Fire safety prevention and coordination, Acoustics & energy savings, Synthetic management, Project waste environmental management Completion deadline: 2009 - 2012 |
![]() |
|
| Losail
Campus (Qatar) 210,000 mē Project owner: QATAR FOUNDATION - Delegate project owner: QATAR PETROLEUM Architect: Roger TAILLIBERT Nature of the operation: Construction of the Academy of Excellency delivering an international bachelor's degree, including housing (residential school, allowance housing, and villas), sports fields, swimming pools, etc. Mission: Engineering study, from sketch to market signing (bid for tender in EXE phase), Fluids engineering, Structure engineering, Electrical engineering, Savings of the engineering lots Completion deadline: 2008 - 2010 |
![]() |
|
| Jussieu
University Campus in Paris (75) €65 MILLION - 60,000 mē Project owner: EPA JUSSIEU Associated partners: Guy AUTRAN & Wladimir MITROFANOFF Architects / CASSO Sécurité / GLEEDS Economie Nature of the operation: - Design and construction of provisional buildings to be used for the duration of the site - Asbestos removal, making safe, and rehabilitation of eight blocks of the library (Theory sector) - Asbestos removal in five extra blocks (Geology sector) Mission: Prime contractor for all building trades - Technip TPS agent of the MOE group - Management of works Completion deadline: 1998 - 2005 |
![]() |
|
| Kyoto
High School in Poitiers (86) €31.5 MILLION - 16,500 mē Project owner: POITOU - CHARENTES REGION Architect: SCAU (Guy AUTRAN & François GILLARD) Nature of the operation: Construction of a professional high school - High Environmental Quality operation Mission: Prime contractor for structural and technical contracts Completion deadline: 2006 - 2009 |
![]() |
|
|
Fonsorbes High School (31) €14.9 MILLION - 10,900 mē Project owner: REGION MIDI-PYRENEES Architects: SCAU (Guy AUTRAN & François GILLARD) and Pierre AZEMA Mission: Prime contractor for structural and technical contracts Completion deadline: 2005 - 2008 |
![]() |
|
|
E.N.S.O.S.P.
in Aix en Provence (13) €29.7 MILLION - 27,000 mē Project owner: E.N.S.O.S.P. Architects: SCAU (Guy AUTRAN and François GILLARD) - ATELIER 9 Nature of the operation: Construction of the educational and administrative section of the National Institute of Firemen Officers: educational buildings, administrative buildings, sports buildings, accommodations, catering Mission: Technical design and engineering project management with conception, realisation and follow up of the technical work realisation on new buildings (all the buildings except accommodations and catering) Completion deadline: 2006 - 2009 |
![]() |
|
| Making
safe the Porte des Alpes Campus in Lyon (69) €11 MILLION - 30,000 mē Project owner: LYON 2 University Architect: Michel TURBINE Nature of the operation: Removal of equipment, asbestos removal, making safe, and complete redevelopment Mission: Prime contractor for all building trades Agent for the MOE team - Management of works Completion deadline: 2002 - 2009 |
![]() |
|
| Nice
Saint Jean d'Angely University (06) €13.4 MILLION - 10,000 mē Project owner: RECTORAT DE NICE Architects: G. AUTRAN - BRANTE & VOLLENWEIDER - GOMIS & MACE Nature of the operation: Construction of the Saint-Jean d'Angely University Centre that houses education in Psychology, 1st year Medicine, and Ontology Mission: Prime contractor for technical contracts Completion deadline: 1995 - 1997 |
![]() |
|
| Paris
Dauphine University in Paris (75) €7.7 MILLION - 7,000 mē Project owner: REGION ILE-DE-FRANCE and VILLE DE PARIS Architect: S. ANSPACH (A.C.H.R.) Mission: Prime contractor all building trades for the extension of research rooms and classrooms with 3 amphitheatres Completion deadline: 1992 - 1994 |
![]() |
|
| Vienne
Polyvalent High School in Saint Romain en Gal (69) €16 MILLION - 15,400 mē Project owner: RHÔNE-ALPES REGION Architect: Atelier d'Architecture Bernard PARIS Nature of the operation: Heavy restructuring in an occupied environment of general classrooms, scientific and tertiary classrooms, administration, works accommodation, school rooms and CDI Mission: Prime contractor for technical contracts (structures, fluids) and VRD Completion deadline: 2005 - 2010 |
![]() |
|
| Paul
Lapie High School in Courbevoie (92) €9.5 MILLION - 12,000 mē Project owner: CONSEIL REGIONAL D'ILE DE FRANCE Architect: Pierre-Louis FALOCI Nature of the operation: Rehabilitation and extension - Operation on an occupied site Mission: Prime contractor for structural contracts, technical contracts and construction economics Completion deadline: 1997 - 2005 |
![]() |
|
| University
residence- INSA Campus in Villeurbanne (69) €13.8 MILLION - 17,200 mē Project owner: OPAC DU RHÔNE Architect: A.A.B.D. (Dumétier) Nature of the operation: Asbestos removal, restructuration and rehabilitation of 364 student apartments and construction of 128 student apartments (939 beds) Mission: Prime contractor for design and completion of technical contracts and asbestos removal - Basic assignment Completion deadline: 2004 - 2008 |
![]() |
|
| Saint-Nazaire
d'Aude College (11) €8.4 MILLION - 4,700 mē Project owner: CONSEIL GENERAL DE L'AUDE Architect: LCR Architectures Nature of the operation: Construction of the 27th college in the Aude: college (4,700 m²), gymnasium (1,672 m²), accommodation (260 m²) Mission: Prime contractor for all building trades - Basic assignment + Execution studies Completion deadline: 2004 - 2006 |
![]() |
|
| Henri
Poincaré High School in Palaiseau (91) €8.4 MILLION - 9,000 mē Project owner: CONSEIL REGIONAL D'ILE DE FRANCE Architects: Catherine MORGOULIS, Cabinet LMT Architects Nature of the operation: Heavy rehabilitation all building trades and extension of a secondary school of 830 pupils, including catering facilities Mission: Engineer assignment all building trades including economics Completion deadline: 2000 - 2004 |
![]() |
|
| Maryse
Bastié College in Décines (69) €4.57 MILLION Project owner: CONSEIL GENERAL DU RHÔNE Architect: Laurent BANSAC Mission: Prime contractor for structural and technical contracts - Basic assignment + EXE studies Completion deadline: 2000 - 2002 |
![]() |
|
| CUST:
Engineering school in Clermont-Ferrand (63) €9.2 MILLION - 10,800 mē Project owner: CONSEIL GENERAL DU PUY DE DÔME CA: SOCIETE D'EQUIPEMENT DE L'AUVERGNE (SEAU) Architect: PANTHEON Nature of the operation: Extension of the Centre Universitaire des Sciences et des Techniques (CUST) and construction of a common centre with the Institut Supérieur de l'Informatique (ISIMA) on the Campus of CEZEAUX: Laboratories, classrooms for practical works, amphitheatres, communal rooms Mission: Engineering assignment all building trades, project economics - EXE studies all building trades Completion deadline: 1997 - 2000 |
![]() |
|