SNECMA Factory at Evry - Corbeil (91)
Client: SNECMA ETABLISSEMENT D'EVRY CORBEIL
This project is made up of a client assistance assignment as part of the modernisation master plan of the site and prime contracting and assistance to the Prime contractor of the subprojects making up the master plan
Nature of assignment n° 1: Time assistance assignment for the drawing up of the site at modernisation master plan: analysis and diagnosis of existing elements, feasibility study, strategic planning, drawing up of calls for tender
Completion deadline: November 2005 - March 2006
Nature of the assignments: Assignments as the Prime contractor for the exterior, a workshop of 88,000 m² and a building of 15,000 m²; assignment assisting the Prime contractor for buildings of 3,500 m² and 3,700 m²
Completion deadline: 2006 - End 2007
 
   
Quadrilatère Richelieu -Historical site of the Bibliothèque Nationale de France in Paris (75)
Client: MINISTERE DE LA CULTURE (EMOC)
Nature of the assignment: Feasibility study and phasing of safety and rehabilitation works of the Quadrilatère Richelieu, historical site of the Bibliothèque Nationale de France in the centre of Paris (buildings from the 17th to 20th century)
Study, estimation, and planning of related transfers and works
Completion deadline: 2005 (2 months)
 
   
Transfer of the Versailles Magistrates' Court and the Appeal Court
to the site of the old Richaud Hospital in Versailles (78)
Client: MINISTERE DE LA JUSTICE (AMOTMJ)
Nature of the assignment: Within the framework of the definition study carried out by three teams of Architects and Engineers, Technip TPS carried out a client assistance assignment for the analysis and validation of the technical choices proposed, as well as for fire safety aspects
Completion deadline: 2004
  Architects: BROSSY, HUIDOBRO, ARTHEME
   
Perspective for evolution of the Port Edouard Herriot in the Lyon metropolitan area (69)
107 hectares

Client: GRAND LYON/CNR/VNF
Urban Architect: François KERN
Risk Study: Technip France
Nature of the assignment: Assistance to the client for the perspectives for evolution of Port Edouard Herriot in the Lyon metropolitan area; determine the evolution of the poor in terms of economics, logistics, security, and town planning
Completion deadline: 2003
  Urban Architect: François KERN
   
Renewal of master plans of the Fos Sur Mer Industrial Estate (13)
3,600 hectares

Cost of development works: short-term €554M - medium-term €188M - long-term €438M
Client: PORT AUTONOME DE MARSEILLE
Urban Architect: François KERN
Landscaper: ILEX
Technical and economical diagnosis of the construction: Technip TPS
Nature of the assignment: Assistance to the client for the renewal of master plans of the Port Autonome de Marseille in the metropolitan area, multidisciplinary studies: socio-politico-economical, town planning and technical to determine the evolution of this geographical zone over 20 years
Completion deadline: 2002
  Urban Architect: François KERN
   
Top of page
Return to the "Areas of expertise" page
   
[Home] [The company] [News] [Services & assignments] [Major projets] [Areas of expertise] [Contacts] [Recruitment] [e-GID] [Technip Group]