Croix Rousse Biology Laboratory in Lyon (69)
€13M - 10,000 m²

Client: HOSPICES CIVILS DE LYON
Architect: Jean-Philippe PARGADE
Project including laboratories of category NSB 3 and NSB 2
Nature of the assignment: Prime contractor for technical and structural contracts, project economics
Completion deadline: 1998 - 2004
  Architect: Jean-Philippe PARGADE
   
DGCCRF-DGDDI Interregional Laboratory at Oullins (69)
€6.9M - 4,500 m²

Client:MINISTRY FOR THE ECONOMY AND FINANCES
Architect: Jacques FERRIER
Project: Laboratory common to Customs management and Fraud Repression management
Agro-food and industrial analysis
- Microbiological examinations, analysis of compositions
- Contamination research
- Tests on industrial products
Nature of the assignment: Prime contractor for technical and all building trade contracts
Completion deadline: 1998 - 2002
  Architect: Jacques FERRIER
   
Institut Claude Bourgelat -National Veterinary School of Lyon in Marcy l'Etoile (69)
€2.8M - 2,250 m²
Client: REGION RHÔNE-ALPES
Architect: FERRAND SIGAL
Project: Construction of the future Compared Biopathology Regional Centre on the site of the National Veterinary School of Lyon
This research Institute shelters an animal centre (180 boxes), 3 surgical rooms and 10 laboratories
Part of the Institute is a level-2 containment area, with processing of liquid waste
Mission: Technical and structural engineering contracts
Completion deadline: 2003 - 2005
  Architect: FERRAND SIGAL
   
Research laboratories in Solaize (69)
€3M - 3,000 m²
Client: INSTITUT FRANÇAIS DU PETROLE (IFP)
Architect: ASYMPTOTE - Pierre SALMON
Project: Construction of several buildings and laboratories, experimentation and research centre for petroleum products and their transformation
Assignment: General prime contractor and construction as property manager
Completion deadline: 1995 - 2001
  Architect: Pierre SALMON
   
Pfizer laboratory in Amboise (37)
€22.9M - 30,000 m²

Client: PFIZER FRANCE - Technip
Project: Restructuration and extension of a pharmaceutical production and logistics centre
Nature of the assignment: Assistance to Technip for covered walled area
Completion deadline: 1995 - 1998
 
   
Laboratory of the Paris National Mines School in Corbeil-Essonnes (91)
€6.7M - 7,000 m² - Prix de la Première Oeuvre 1993 (Construction Award)

Client: SNECMA and Ecole des Mines
Architects: Jacques FERRIER and François GRUSON
Project: Research laboratories for material physics
Nature of the assignment: Joint prime contractor for all of the technical contracts
Completion deadline: 1992
  Architects: Jacques FERRIER and François GRUSON
   