The project

LThe project of the new Bibliothèque Nationale de France (French National Library) was designed to replace the historical Quadrilatère Richelieu site, located in the centre of Paris. The latter, made up of old and often-modified buildings, had become both too cramped and less and less suited to the functions of conservation, enriching of contents, specialised research, and public use.

The new Bibliothèque Nationale is located on the site of Tolbiac, alongside the Seine, in a previously industrial sector of the capital that is undergoing a vast urban rehabilitation.

This new unit is made up mainly of a base, receiving a vast public esplanade and surrounding a garden, as well as four towers in the shape of open books with a fully glazed facade.

The library has more than 2,000 reading places for researchers and more than 1,500 places for the public. It covers some 350,000 m² of floor area. Studies started in 1990 and it was opened by the President of the Republic F. Mitterrand in April 1995.

The operation represented a total investment by the state of more than €1 billion, of which approximately €600M excluding VAT was for the construction itself.

The Client ETABLISSEMENT PUBLIC de la BIBLIOTHEQUE de FRANCE
 
PUBLIC ESTABLISHMENT of the BIBLIOTHEQUE de FRANCE   Dominique PERRAULT, Contracted Architect
Technip TPS, Project management and Engineering of technical contracts
SECHAUD & BOSSUYT, Structural Engineering
SYSECA, Engineering of Low Current and Automatic Document Handling contracts
HGM, GTC Engineering
 
The assignments of Technip TPS   Technip TPS carried out the full range of management and technical engineering assignments of the project.
   
 
General coordination of Prime Contracting:
- Organization.
- Planninf.
- Cost control.
- Administrative management.
Fluid engineering:
- Production and distribution of hot (5 MW) and cold (16 MW) fluids.
- Plumbing - Fluids (1,500 sanitary appliances).
- Waste processing.
- Mass catering (2 x 1,000 covers).
- Mechanical appliances (120 air processing units).
   
Electrical engineering:
- Normal production and distribution (40 MVA).
- Backup production and distribution (6 MVA).
- Lighting, low voltage distribution.
- High-quality supply.
  Electromechanical equipment engineering (100 appliances):
- Lifts and freight lifts.
- Escalators and travelators.
   
Design of the common computing system:
- Specification of the system.
- Supplier calls for tender - Acceptance.
- Organization and procedure.
- Management of operation and maintenance.
  Management of the summary cell:
- Organization and procedure.
- Planning.
- Administrative management.