The project concerns the processing of asbestos, the making safe, and the
rehabilitation of the technical installation building on the Jussieu University
Campus, made up of classrooms and research laboratories for geology, chemistry,
mathematics, and physics.
Our intervention, within the framework of a vast project that is still in
progress, successively dealt with:
- The building of temporary buildings for teachers and researchers
during the renovation of the Campus.
- The rehabilitation of a first phase of eight blocks (theory sector)
and of the library.
- The removal of asbestos from a second phase of five blocks (geology
sector).
The first phase of the operation represents an investment of €65M excluding
VAT for the rehabilitation of 60,000 m².
| The
Client |
 |
NATIONAL
MINISTRY FOR EDUCATION, represented by THE JUSSIEU CAMPUS PUBLIC ESTABLISHMENT
|
| Prime
contractor |
|
Technip
TPS, Engineering contract holder for structure contracts, technical
and asbestos removal contracts
Guy AUTRAN and Wladimir MITROFANOFF, Architects
Cabinet CASSO, fire safety expert
GLEEDS international, Economist
|
The
assignments of
Technip TPS
|
|
|
Preliminary
studies for all of the site:
- Technical analysis of buildings.
- Technical and architectural feasibility studies of the project.
- Fine tuning general scenario for the entire project. |
|
Prime
contracting of the first phase of the operation:
- Pre-project and project studies.
- Consultation of companies and assistance with the signing of works
contracts.
- Approval of work execution studies carried out by the companies
and management of the study summary cell.
- General organization of the site.
- Management of works.
- Organization and management of approval of works and files concerning
work carried out.
- Budgetary monitoring of the site. |
 |
|
|
|
|